Core vocabulary for scheduling: activity (work taking time + resources), milestone (zero-duration checkpoint), float (slack — how much an activity can slip), critical path (longest activity chain — slack = 0).
Is a part of the project that requires resources and time
Is the completion of an activity that provides evidence of a deliverable completion or end of a phase - is an event that takes zero time.
Is the amount of time that a task can be delayed without causing a delay to subsequent tasks
Is the amount of time that a task can be delayed without delaying project completion
Is the longest continuous path taken from the initial event to the terminal event
Is an activity where total slack is zero