Compare what you planned to have done, what you actually have done, and what it has cost — to get objective cost- and schedule-performance numbers and forecast where the project will land.
Key formulas
PV (Planned Value) = budgeted cost of work scheduled
EV (Earned Value) = budgeted cost of work performed
AC (Actual Cost) = actual cost of work performed
CV=EV−AC (cost variance)
SV=EV−PV (schedule variance)
CPI=EV/AC (cost performance index; <1 = over budget)
predict future project performance based on current/past performance
Results can be expressed in dollars and/or performance
Planned Value (PV)
The portion of the approved cost estimate planned to be spent on the given activity during a given period.
Earned Value
The value of the work actually completed
Actual Cost
The total costs incurred in accomplishing work on the activity in a given period
Example
You are assigned to manage a project that is planned to finish in 12 months, estimated to cost 100,000.Attheendofthethirdmonth,basedontheprojectGanntchart,20hasreportedthecostoftheprojecttodateas35,000.
PV = (100_000\*3)/12 = \25_000
EV = (100_000\*20)/100 = \20_000
AC = $35_000